The ICI Program Expansion and Ontario’s Electricity Market

September 28, 2020  By Greg Young


The Industrial Conservation Initiative (ICI), a program that began in Ontario back in 2010 to allow large consumers to save on the Global Adjustment cost by reducing consumption during provincial peak events, has been under review by government and stakeholders, leaving uncertainty in its future.

When the ICI began in 2010, the eligibility requirement was a building that had an average 12-month peak demand of 5-MW or greater. In 2015, the program slightly expanded by lowering the demand requirement to 3-MW. In January 2017, the program further expanded to allow buildings with a 1-MW or greater demand. In April 2017, the most recent change was made to allow specific manufacturing/industrial buildings to opt in with a 500-kW (0.5-MW) average annual peak demand.

The two changes in early 2017 had profound effects on the ICI program, allowing more buildings to become eligible, changing the dynamics of the provincial peaks and a continuing to shift electricity costs to the smaller Class B rate payers.

Global Adjustment: Class A vs B

The ICI program is centred around the Global Adjustment (GA) fee, which is paid by both Class A rate payers (those that opt in to the ICI), or by the smaller-medium buildings that aren’t eligible for the ICI program (50-1,000-kW demand), known as Class B. As shown below, the Class B buildings pay far more towards the GA than Class A.

Advertisement
No alt text provided for this image

From the above, we also see that in 2017 and 2018, the Class A rate payers are now paying a higher percentage towards the total GA amount, suggesting that more buildings did in fact opt in to the ICI with the new lower peak demand eligibility requirements.

ICI Participation: Post 2017 Expansion

The Global Adjustment data from the IESO was first analyzed to determine how many buildings are participating in the ICI. The methodology included determining a province wide Peak Demand Factor (PDF) that can be used to determine the average cumulative demand by all ICI participants during the top five peak days.

No alt text provided for this image

The above graphic illustrates that in 2017, after the ICI program expansion, participants grew by a significant amount with approximately 6 per cent of the provincial peak day demand shifting from Class B to Class A. In 2018, participation grew slightly more which could be attributed to more organizations now being aware of the new ICI program and rules, or simply that buildings didn’t perform as well during the provincial peak days. Overall, since the 2017 ICI expansion, a significant amount of the electrical demand during the provincial peaks shifted from Class B to Class A rate payers. But how did the costs shift?

The Debate

If we go back to the first line of the article, it was described that the ICI was introduced so larger consumers could save on Global Adjustment costs by lowering their demand during the provincial peaks. The savings are great for ICI participants, but the overall GA amount doesn’t reduce itself, it still has to be paid. The ICI mechanism simply shifts costs to Class B rate payers, and as ICI participation grows (and more buildings get better at reducing peaks), costs will continue to shift down to Class B rate payers to cover the remainder of the GA bill. The cost savings for Class A rate payers is outlined below when comparing the percentage that ICI participants pay towards the GA in relation to their total annual electricity consumption.

No alt text provided for this image

The above paints an important picture, showing that the Class A buildings pay a significantly less percentage towards the GA compared to the amount of electricity they consume annually. In 2018 for example, with the ICI expansion well underway, Class A rate payers were consuming nearly one third of the electricity compared to Class B, while only paying about one fifth of the Global Adjustment amount, further illustrated below.

No alt text provided for this image

The theme of the debate is clear: Class A buildings pay less per unit of energy than Class B does (Class A, 2018: $51/MWh | Class B, 2018: $88/MWh). The imbalance between energy consumption and costs leads to a constant debate on the fairness of the ICI program. As ICI participants get better at reducing peaks, costs will only continue to shift even more to Class B rate payers.

Industrial Price Consultations: Stakeholder Feedback on the ICI

Throughout 2019, the Ontario government held electricity price consultations for industrial stakeholders to ensure “Ontario’s industrial consumers have a fair and stable pricing framework that allows them to focus on their core business”. The main theme of the consultation was centred around the ICI program, with key points summarized below:

  • Some ICI participants have invested in behind-the-meter generation/storage to lower GA costs, and eliminating the ICI could leave many stakeholders with stranded assets.
  • Some stakeholders suggested the ICI has become too big (the growth of the program was illustrated in this article), making it more difficult to predict the top five provincial peaks.
  • Stakeholders suggested the overall GA amount has grown too large, increasing costs for both Class A and B rate payers. This seems to have motivated a recent Ministerial Directive to have the IESO hire third party support to review generation contracts to find savings in GA costs.
  • Some stakeholders mentioned the loss in revenue by shutting down production to miss peaks was not sustainable. These type of buildings are prime candidates to invest in generation or storage, however, many stakeholders mentioned that the uncertainty in the ICI’s future was an obstacle for management to approve such an investment.
  • Stakeholders suggested that the AQEW adjustment that occurs 20-business days after a potential peak event provides further challenges in predicting the ICI peaks (especially when the hour ending of the peak shifts).
  • Stakeholders suggested information provided “on the IESO’s website should be clearer since consumers rely on that information to make business decisions.” Easily accessible information and business case analysis on the ICI program was the inspiration for interval-energy.com.

What’s Next?

The ICI program is still intact with no clear direction from the Ontario government on next steps with industrial rates moving forward. The newest top five peaks for the 2019-2020 peak setting period have likely been set, so organizations should start understanding how they performed this past summer to start budgeting for the new Class A costs starting in July 2020.

Greg Young is a manager of engineering at CoEng Advisors Inc. based in Toronto.